How to Quote a Re-Roof When You Can't See What's Under the Iron — the Hidden-Damage Clause That Stops You Wearing the Loss

Re-roof quotes go wrong when you price the steel but ignore what's under it. How to use provisional sums and a hidden-damage clause so you don't wear the loss.

Category: Quotes & Invoicing | Read time: 7 min read


You're standing on the roof of a 1960s weatherboard in Ipswich, quoting a re-roof, and the sheets look straight from the ground — the colour's faded, sure, and there's a bit of lifting around the ridge — but the client's already decided the roof needs replacing and they're shopping three prices. The problem is what you can't see from here: the battens that have been rotting out underneath for a decade, the sarking that got torn when the last person did the solar, and the rafters that are going to need sistering the moment you strip the iron and finally get a look at them.

That's the re-roof game, and it's where roof plumbers lose money that was never in their quote to begin with.

The Sheet Price Is a Red Herring

A customer ringing around for re-roof prices is almost always comparing the wrong number — the square-metre rate of the new iron — because that's the only part of the job they can hold still in their head. ColorBond versus Zincalume, 0.42 versus 0.48 gauge, Lysaght versus whatever the cheaper import is. But the steel is the most predictable line in the whole job; you can price it to the cent from the plan, and it'll be there on the day.

What costs you money is everything between the old roof coming off and the new sheets going back on, none of which you can quote accurately until the old roof is actually in the skip. A roof plumber who's been doing re-roofs for a few years learns to price the known and wrap the unknown in language that protects the margin — and the roof plumber who hasn't, quotes the steel, hopes for the best, and wears the batten replacement out of their own pocket when they find the sarking's been gone since the last storm.

What You'll Find Once the Iron Comes Off

The Battens Nobody Looked At

The battens carry the sheets, and on a roof that's been up forty or fifty years they're usually the first thing to go. Water gets in through a lifted sheet or a rusted washer, sits against the batten, and rots it from the top down where you can't see it. The moment you strip the roof you'll find a percentage of battens that need replacing — sometimes a handful, sometimes the lot — and there is no way to put that number in a fixed quote honestly.

The only honest way to price it is a per-metre rate for batten replacement, flagged as provisional. You tell the client up front: "Battens are $X per linear metre if we need to replace them, most re-roofs of this age run somewhere between twenty and sixty per cent replacement, you'll see exactly how much on the day before I order the extra." They can't argue with it later if it's sitting there in black and white on page two.

The Sarking That's Gone

Sarking does a few jobs on a metal roof — it's a vapour barrier, it stops condensation dripping onto the insulation, and it's the last line of defence when driving rain gets pushed up under the overlap in a storm. On a lot of older houses it either wasn't installed in the first place or it's torn and hanging like a flag, which means a re-roof is the one chance the client gets to put it right while the roof's open.

If the quote assumes the old sarking's fine and can just stay, and the day-of reality is sarking that disintegrates when you pull a sheet off it, you've either absorbed the cost or you're having the awkward conversation with the client about a variation they thought was included. Price the sarking in or flag it as conditional — never let it ride on assumption.

The Timber You Can't Vouch For

Stripping a roof occasionally reveals the kind of damage you never want to find — termite-eaten rafter ends, water-damaged top plates, a truss that someone with a chainsaw "modified" to fit a skylight in 1989. That's where it stops being a roofing quote and starts being a structural conversation, and it needs a builder or a chippy, not another sheet of iron.

This is the line you draw in the quote itself: structural timber work is outside the scope of a standard re-roof, and any such work discovered on strip-off will be priced as a separate variation before you proceed. It's not you being difficult; it's you making sure a rotten ridge beam doesn't quietly turn your profitable re-roof into a loss.

Provisional Sums vs Fixed Price — When Each Makes Sense

There are two honest ways to price a re-roof, and they suit different jobs.

A full fixed price only works when you genuinely know what's under the iron — a roof you've already worked on, a re-roof over a structure you've walked, or a new build where the battens and sarking are all yours and you know exactly what went in. On those jobs you can sharpen the pencil and give a number you'll still be happy with at the end.

A fixed price plus provisional sums is the answer for the typical older roof where you can't see the substrate. Fixed price covers everything you can measure and guarantee: the steel, the flashings, the ridge capping, the gutters, the labour to strip and relay. Provisional sums cover the variables — battens per metre, sarking per square, insulation, additional timber — with a clear note that they're only charged if and when they're needed, and the client approves before you proceed.

The third option — the one that loses money — is a flat price that quietly assumes the best case and lets reality do the talking. Don't be that roofer.

What the Client Actually Wants to Hear

Nobody likes a quote with variables in it, because variables feel like a trap until someone explains them properly. So explain them. The framing that works is the one that puts you on the same side as the client rather than across the table from them: "I'd rather show you the real cost up front than give you a cheaper number today and a surprise invoice in three weeks."

That one sentence does more than any amount of provisional-sum terminology, because it tells the client you've done this enough times to know what's under the iron — and that the cheaper quote they got from the bloke down the road is cheap precisely because it hasn't accounted for it. When the battens turn out to be rotten, their roofer eats it or hits them with a variation they never mentioned; yours was priced honestly from the start.

The Bottom Line

Re-roofs are the highest-value jobs in roofing — a good one is worth more than a dozen gutter cleans — but the margin lives or dies in the gap between what you can see from the ground and what's actually under the iron. Price the steel to the cent, wrap the battens, sarking, and timber in provisional sums the client has already agreed to, and leave a clear line in the quote about structural work being outside scope.

The roofers who make money on re-roofs aren't the ones who found the lucky roofs with nothing wrong underneath — they're the ones who wrote a quote that was still profitable when there was plenty wrong underneath, and told the client why before they ever lifted a sheet.


Trade Track helps Australian tradies manage quotes, jobs, and invoices so you spend less time on paperwork and more time doing what pays. No credit card required · 7-day free trial.

Ready to run your trade business smarter?

Trade Track helps Australian tradies manage quotes, jobs, and invoices from one simple platform — so you spend less time on admin and more time on the tools.

Start Free Trial →

No credit card required · 7-day free trial

← Back to Blog